The fourth largest sewer utility in the United States, Metropolitan St. Louis Sewer District (MSD) is currently under a Consent Decree with the U.S. Environmental Protection Agency and the Missouri Coalition for the Environment to control sanitary sewer overflows (SSOs) within the Deer Creek Watershed. In response, MSD is directing the design and construction of the Deer Creek Sanitary Tunnel and the Deer Creek Pump Station as part of system improvements for the 23-year, $4.7 billion Project Clear program.

Gresham Smith was selected to design the $39.2 million deep pump station, which will comprise a wet well, an influent sump, and two dry wells and a screening structure to be located in three separate 36-foot-diameter vertical shafts, approximately 185 feet belowground. The pumping and screening facilities will receive flow from the Deer Creek Sanitary Tunnel currently under construction.

Client

Metropolitan St. Louis Sewer District

Location

St. Louis, MO

Project Type

Wastewater

Services

Engineering

Accolades

Showcase

28

mgd pump station

48

million gallon deep-rock tunnel

36

36-foot-diameter vertical shafts

The Advantages of BIM

The Advantages of BIM

Gresham Smith’s three-shaft pump station solution meets MSD’s needs at a lower cost and higher level of service than that of a typical deep pump station by utilizing a separate shaft for the wet well and each dry well. The unique nature of the design posed a challenge for our multidisciplinary team spread across several Midwestern states. To keep all team members up-to-date with the most current design configuration, the project was developed as a 3D Building Information Model (BIM) and maintained on a shared server. This approach provided added value to the client by allowing MSD to incorporate the 3D model into their asset management program
Cost Effective, Resilient and Flexible

Cost Effective, Resilient and Flexible

Through some out-of-the-box thinking, our innovative solution not only redefines the design of a traditional deep pump station but also the type of software used in its development. The end result is a cost-effective, resilient and flexible design solution capable of dewatering the 48-million-gallon Deer Creek Sanitary Tunnel in less than 48 hours.

Testimonials

“Gresham Smith really addressed all of our needs during the design of the pump station. ”

Brad Nevois, Assistant Director of Engineering, Metropolitan St. Louis Sewer District

Gallery

MSD provides St. Louis a metropolitan-wide system of wastewater treatment and sewerage facilities for the collection, treatment and disposal of sewage.
The site of the Deer Creek Sanitary Tunnel and Pump Station under construction.
The site of the Deer Creek Sanitary Tunnel and Pump Station under construction.
The three-shaft solution provides construction cost savings and operational flexibility and resiliency.
The 36-foot-diameter shafts are approximately 185 below ground.
The site of the Deer Creek Sanitary Tunnel and Pump Station under construction.
Pump station shaft excavation.

MSD provides St. Louis a metropolitan-wide system of wastewater treatment and sewerage facilities for the collection, treatment and disposal of sewage.

Project Contact

Our team develops creative solutions for the world's toughest infrastructure problems.

Learn more about our Engineering expertise.

Craig Parker, P.E., ENV SP
Craig Parker, P.E., ENV SP
Senior Vice President